OPM (ORACLE PROCESS MANUFACTURING)
GAYAKAVADA PAVAN KALYAN RAO
OPM
(ORACLE PROCESS MANUFACTURING)
PRODUCT
DEVELOPMENT
Oracle Process
Manufacturing (OPM)
v Process Manufacturing is a Production of Goods in a Bulk Qty.
v Industries use thus method to Manufacture goods like foods and
Beverages, chemicals and etc.
v OPM uses Recipes, Formula, Routings and Operations.
v Formula, Routing and Operations are Mapped to each other while
creating Recipes
Modules that are Integrated with OPM
Ø Inventory
ü
Set up organizations, Sub
Inventories, Locators, Items, Unit of Measure types, Conversations
Ø
Product Development
ü Setup Formula,
Recipes, Operations, Routings
Ø
Process Execution
ü Create Batches,
Ingredients Picking, Batch Production, Batch completions
Ø
Quality Management
ü Create
Specifications, Test, Samples, Test Results
Ø
Cost Management
ü Setup Item cost,
Cost Rollup, Period End Processing
Ø
Execution system for Process MFG
ü Viewing/Controlling
Batch Records, Printing Labels
Oracle Inventory
Ø Set up
organizations, sub inventories, locators, items, unit of measure types, units
of measure, and picking rules. Refer to the Setting Up chapter for more
information.
Ø Set up required
profile options as described in the Oracle Inventory User's Guide.
Create a Master
organization
Nav->Inv->setup->organization
And give the details as AND create a child org also
Here to make
OPM – Org, enable Process Manufacturing
Then define control setups
Create sub
inventories and define locators
NAV->INV->Org->Sub inventory
Now define
UNIT OF MEASURE CLASSES(UOM)
NAV->INV->Setup->Org->Unit of
Measure->Classes
Give the details as shown below. Then click on the Unit of Measure tab
Give the details as shown below and click on Conversions tab
Give the details as shown below
Now define a
new value set for Item Categories
NAV->INV->Setup->Flexifields->Validation->sets
Now define the Categories sets
Set it as a
Default Category
NAV->INV->Items->Category Sets
Now define
Default Category Sets
NAV->INV->Categories->Default category sets
Now define
an Item and Make sure to enable required check box in Process Manufacturing tab
and give UOM
NAV->INV->Items->Master Items
Check
whether item category is derived or not
Tools -> Category Assignments
Now we have to Define few items like that
Product Development
Ø Set up Product
Development parameters, formulas, recipes, operations, routings, activities,
resources, and validity rules. Refer to Setting Up for more information.
Ø Set up the
required profile options as described in the Oracle Process Manufacturing
Product Development User's Guide.
Now let’s
define classes for FORMULA, OPERATIONS and ROUTING
Now define FORMULA CLASSES
Go to Formulator Res -> Setup -> Formula Class
Now define PROCESS OPERATION CLASSES
Go to Process Engineer Res -> Setup -> Process Operation Classes
Now define
the PROCESS ROUTING CLASSES
Go to Process Engineer Res -> Setup -> Process Routing Classes
Now let’s define Org
parameters for
Product Development
Nav->Product Development
Security Manager Responsibility->organization->parameters
Give the details as shown in the below screen shots
FORMULA:
Ø Formulas are lists of ingredients and products with their associated
quantities and processing instructions.
Ø In some case, we can refer to formula as a Process manufacturing
list.
Ø Production batches are based on formulas defined in the product.
Now Let’s
Define FORMULA
NAV->Formulator
res -> Formula
Give the details as shown below
After defining the Item give the related Ingredients to the Item
Now change
the status of the Formula
Action -> Change Status
Change
status to Approved for General use
Ø New to make changes
at any time, assuming you have security access. Default.
Ø Approved for
Laboratory Use for use in laboratory batches and cost rollups for the
laboratory.
Ø Approved for
General Use for use in production batches.
Ø On Hold to specify the
object cannot be used until the status is changed.
Ø Frozen to prevent any
further changes to the object and any dependent data.
Ø Obsolete/Archived to specify the object can no longer be used unless the status is changed.
To see our Formula, click on Formula Workbench
RESOURCES
Resources
are the assets to produce batches, including production equipment and employee
labour
Now let’s
define RESOURCES
NAV->Process Engineer Responsibility->Setup -> Generic Resource
Now define PROCESS PARAMETERS
Setup -> Process Parameters -> Define Parameters
Now Assign
this Parameters to Resource
Go to Resource
At same way we have to define another Resources
ACTIVITIES
Ø Activities are
actions performed during production. Set up activities to divide a
manufacturing process into logical breakpoints.
Ex: cooling, mixing
Now define
Activities
Setup -> Activities
OPERATIONS:
Ø Operations are a
combination of one or more activities performed in a production batch and the resources
used to perform those activities.
Now define OPERATIONS
NAV->Process Engineer -> Process Operations
Under Operations We give our Activities
Now Change Status to Approved for general use
PROCESS
ROUTING
·
A Routing is a sequenced set of
operations performed to complete a production batch.
·
The operations are presented in
a series of steps that organize the operations into an orderly set of
activities that have individual resources associated to them.
Now Let’s
define ROUTING
NAV->Process Engineer -> Process Routing
Give the Operations
Now change the status
Now go to
the Workbench and see the status of the Routing
Now click on the Designer tab for checking the routing
RECIPE
Ø Recipes standardize the structure of all information that describes
production of one or more products.
Ø They are linked using a recipe and its validity rules.
Now let’s
Define the RECIPE
NAV-> Formulator responsibility -> Recipe
After entering required details change the status
To view Recipe Summary, go to Formulator Workbench
PRODUCT EXECUTION
Go to Production
Supervisor responsibility
Go to Setup -> Parameters
In Document Numbering tab give the required data
Now we’ll
create a Production Batch
Go to Production Supervisor -> Create Document
Select Document type and In Total Input tab enter the required data
To view our Batch, go to Workbench and View
Now we do Release for the Batch
Go to Batch
Detail give document number and find
Here click on Actions -> Release - OK
Then the
Status changes to WIP
Now click on the steps tab
Now we Release Step click on Actions – Release Step
Repeat the
same process for all Steps
Now we can see the step status is chanced to WIP
Now Transact Material click on Transact tab
Select Item and Enable Transact, give Sub-Inv, Qty then click on Transact
Repeat the same process for all Items
Now Enter Process Material click on Steps
then select the line and click on Activities
Select the line and click on ResourcesNow select the line and click on Process Parameters
Here enter the Actual Value and Save
Now Complete Batch click Actions – Complete - Ok
Now we can see status as Completed
Now Close Batch click on Actions – Close - OK
To view our Batch, go to Workbench and view
GAYAKAVADA PAVAN KALYAN RAO
Comments
Post a Comment